Our plans are currently in the process of getting approved by the city for permits and then we will begin getting our loan secured. The new Children's ministry building has been designed and Tyler Building Systems will be begin fabricating the parts. 

 

Schedule and Timeline of Construction

Feburary: Dirt work and slab for the Children's Ministry Building begins.
Feburary - March: Covered Portico   
March - April: Construction of Children's Ministry Building 
May - July: Renovations of the Faith and Life Center begin (gym)
July-November: Renovations of the main church offices, ECM classrooms and offices, and the Commons area. 

 